Foressa Mountain Town Construction Updates Q1 2023
Site development
Land development of Phase 1A is 100% complete, while Phase 1B is at 65% progress ahead of schedule.

Amenities
Target completion for Main Pavilion by Q2 2023, Main Entry Signage by 3Q 2023, and Outdoor Camping Grounds by 4Q 2023.

Turnover
89 lots have been turned over to vecinos.